XRT-CDC Modular & Prefabricated | UPS Solutions

Containerised Data Centres & Switchrooms for Defence, Mining & AI

Mission-Critical Containerised Infrastructure, Australia-Wide


10ft, 20ft, 40ft, Dual Bay & Multi-Container

Air & Liquid Cooling, 10kVA to Multi-MW UPS

Design, Supply, Install & 24/7 Support

UPS Solutions designs, supplies and installs the XRT-CDC range as three payload types: containerised data centres with IT racks and precision or liquid cooling, containerised switchrooms carrying switchgear and distribution, and power train units integrating transformer, UPS, batteries and output distribution as one factory tested module.

20+ years • 100,000+ UPS units supported • 24/7 support

Containerised Data Centres, Built & Tested in the Factory

Delivered and Supported Australia-Wide

A traditional data centre build means a slab, a building fabric, a mechanical contractor, an electrical contractor and a commissioning window measured in quarters. The XRT-CDC range compresses all of it into a factory process, so what arrives on your site is a finished, witness-tested facility rather than a construction project.

Racks, precision cooling, UPS, batteries, distribution, fire suppression, access control and monitoring are installed and proven under load before the container leaves the floor. Site works reduce to footings, a supply connection, a data path and final commissioning, whether that site is a mine in the Pilbara, a forward defence position, an offshore support base or an AI compute cluster.

Need a containerised data centre scoped or costed?

  • Free heat-load & power assessment
  • Configuration & sizing to your brief
  • Factory acceptance testing
  • Install, commission & 24/7 support
Download the XRT-CDC brochure (PDF)
XRT-CDC containerised data centre, dual bay unit with upper module, at the factory before dispatch
Inside an XRT-CDC containerised data centre, cooling units and racks on a raised access floor

Inside the rack row

Cutaway view of an XRT-CDC containerised data centre showing racks, cooling and power

Cutaway, 20ft all-in-one

One Container, a Double Bay, or a Container Park

Modularity is only useful if the second unit costs less effort than the first. Deployments are planned so distribution, cooling headroom and monitoring are sized for the end state, and each expansion is an addition rather than a rebuild.

All-In-One Solution
XRT-CDC 10ft all-in-one containerised data centre
10FT
XRT-CDC 20ft all-in-one containerised data centre
20FT
XRT-CDC 40ft all-in-one containerised data centre
40FT

A complete data centre in one enclosure. IT racks, wall mounted cooling, AC and DC power, battery storage, distribution, monitoring and fire protection, built and load tested before it ships.

Available in 10ft, 20ft and 40ft. IP55 rated and thermally insulated for deployment from -40°C to +55°C ambient.

Dual Bay Solution
XRT-CDC dual bay containerised data centre
2 x 40FT

Two containers joined along their length to make a single room 4876mm wide. Racks face in from both sides onto a true central contained aisle, which is how a 2 x 40ft bay reaches up to 32 racks.

Integrated racks, cooling, power, battery systems, distribution, monitoring and fire protection, IP55 rated and thermally insulated.

Multi Container Solution
XRT-CDC multi container data centre campus
Campus

Dedicated modules for data halls, power rooms, monitoring spaces, lobbies and support functions, linked into a single site. This is where megawatt scale AI and mining deployments live.

Campus style deployment with IP55 protection and thermal insulation, scaled by adding modules rather than rebuilding the original units.

Built for the Site, Not the Server Room

Every XRT-CDC ships as a hardened enclosure before anything is installed inside it. These are the protections that decide whether a container survives a decade on a mine pad, a coastal support base or a forward position.

IP55 sealed

Dust and water protection to IEC 60529, so the IT space stays clean on an open mine pad.

C5M corrosion protection

Optional high durability coating with 750 hour alternating salt spray resistance for coastal and offshore sites.

Ballistic rated

Optional ballistic protection on the enclosure for defence and secure government deployments.

Fire rated to 120 minutes

Fire rated construction options, VESDA class aspirating detection and FM200 or Novec 1230 clean agent suppression.

Rock wool insulated

1.6mm steel plate walls and a 4mm stainless steel floor, with heat transfer held at or below 0.4 W/(m²·K).

-40°C to +55°C

Rated for continuous operation across the full Australian range, from alpine to Pilbara ambient.

Dual bay XRT-CDC containerised data centre, both bays open showing installed racks

Steel plate walls, insulated panels and a sealed floor. The enclosure is built and hardened before anything is installed inside it.

Plan View of Each Configuration

Drawn to true relative scale, so the footprints compare honestly.

Swipe the diagram sideways to see all of it

Plan view of the selected XRT-CDC containerised data centre configuration
Racks
Length
Internal width
Footprint

IT rack Wall mounted cooling Cold aisle Hot aisle / return UPS, battery & distribution

Why the Layout Matters More Than the Label on the Door

Roughly twice the IT in the same steel box

A conventional container splits the box in two and gives half of it to a condenser section. The XRT-CDC keeps the cooling on the wall and runs the racks as a single row on sliding rails, which is how the same footprint ends up holding roughly twice the IT.

Cooling is mounted inside the container envelope before shipping, so nothing is loose on the roof, transit damage drops and commissioning on site is shorter. Racks run out on rails for front and rear access, so a technician is not working blind in a narrow aisle, and cable management and airflow paths both improve as a result.

Hot and cold channels are sealed so supply air cannot short circuit back to the return, which is what holds rack inlet temperatures stable at high density. Full containment is optional and is CFD modelled against the specific rack layout and heat load.

Conventional layout
Conventional container layout with a split condenser section holding four racks
4 racksin a 20ft box
XRT-CDC layout
XRT-CDC layout with wall mounted cooling holding eight racks in the same container
8 racksin the same 20ft box

Wall mounted cooling releases the floor area a split condenser section would otherwise consume.

35%

More usable rack space

Where a conventional container layout takes four racks, the XRT-CDC layout takes eight.

25%

Lower energy consumption

Free cooling and modulating EC fans cut the energy needed to hold the same rack inlet temperature.

20%

Faster deployment

Prefabrication and factory acceptance testing move the build off your site and into the factory.

Cooling Sized to the Load and the Site

Container cooling is not one product. A 5kW per rack comms container in Adelaide and a 100kW per rack training cluster in the Pilbara need different machines, so we size it rather than force one architecture on every project.

Side mount cooling solution for a containerised data centre

Side & Wall Mount Cooling

5.5 – 31.5 kW

  • Highest usable rack density per container
  • Secured for shipping, minimal site commissioning
  • Independent internal and external loops keep dust out
Explore wall & side mount →
Top mount cooling solution for a containerised data centre

Top Mount Cooling

Sized to load

  • Maximum internal wall space retained
  • Good fit for tightly grouped container parks
  • Serviced from roof level walkways
Explore the cooling range →
In-row precision cooling units installed either side of the rack row inside an XRT-CDC containerised data centre

In-Row Cooling

5.6 – 90 kW

  • Close coupled to the heat source
  • Handles high density racks inside a mixed row
  • Scales by adding units rather than resizing plant
Explore in-row cooling →
Room cooling solution for a containerised data centre

Room Based Cooling

5.5 – 122.9 kW

  • Suits dual bay and multi-container halls
  • Highest single unit capacity
  • Straightforward N+1 and 2N redundancy
Explore CRAC units →
Energy efficient fully integrated cooling systems

Fully Integrated Systems

Factory installed

  • Cooling wired, charged and tested before dispatch
  • Monitored through the same DCIM platform
  • N+1 redundancy as standard
Explore modular cooling →
CRX4 liquid cooling for AI and high density racks inside a containerised data centre
Built for AI & high density

Liquid Cooling for AI and HPC Racks

Air runs out of headroom somewhere around 30 to 40 kW a rack. GPU training racks start where air stops, so the heat has to be taken at the chip, at the rack door or in the tank, not carried across a room. All three are available inside an XRT-CDC container and all three are commissioned by us.

Explore liquid cooling →
CRX4-RDX

Rear door heat exchanger

Bolts onto the back of a standard rack and captures the heat as it leaves. The lowest disruption route to high density.

Up to 65.8 kW per rack
CRX4-DLC

Direct to chip

Cold plates on the processors, fed by a CDU. The route NVIDIA class rack-scale systems are designed around.

100 kW in 4U · CDU to 2020 kW
CRX4-IMX

Immersion

Servers fully submerged in dielectric fluid. Highest density per square metre and no mechanical refrigeration in most Australian climates.

Up to 200 kW per cabinet

Where the Heat Actually Goes

Both sections are the same container width at the same scale. Air cooling manages a room air path. Liquid cooling removes the heat before it becomes room air.

Swipe the diagram sideways to see all of it

Cross section comparison. Air cooled: wall mounted cooling supplies a contained cold aisle, air passes through the rack into a rear plenum and returns hot across the ceiling. Liquid cooled: a coolant loop removes heat at the rack and rejects it outside, with no containment and no room air path. Air cooled Wall mount cooling with aisle containment Containment lid Hot return Cooling Cold aisle Rack Liquid cooled Heat captured at the rack, no room air path CDU loop Supply Return To dry cooler or tower CDU Service Rack, full height The air path has to be sealed to hold rack inlet temperature No containment lid, no cold aisle, no hot return path
Cooling unit Cold aisle Hot return IT rack Coolant supply Warm coolant return
Direct free cooling with hybrid air technology in a containerised data centre

Direct free cooling with hybrid air technology reaches a PUE as low as 1.1 in favourable conditions. Indirect free cooling reaches 1.2.

Energy efficient fully integrated cooling systems for containerised data centres

Mechanical mode EER of 3.9, rising to 28.9 in free cooling mode, with R134a refrigerant and no water consumption.

EER figures are typical, based on 37°C return air at 35°C ambient in mechanical mode and 5°C ambient in free cooling mode. PUE depends on load, climate and configuration.

From a 10kVA Comms Hut to a Multi-Megawatt Container Park

The same integration approach carries across the whole range. What changes is the UPS topology, the battery chemistry and how many containers share a distribution spine.

3 – 60 kVA

Rack Mount UPS

Online double conversion in the IT rack itself. Suits remote comms shelters, edge nodes and single rack deployments.

60 – 200 kVA

Modular Rack UPS

Hot swappable power modules with N+1 redundancy inside a standard rack footprint. Capacity grows by adding modules.

250 – 600 kVA

Modular Floor UPS

Floor standing modular systems for compute halls and high density containers. Configurable to Tier I to IV distribution.

60 – 1200 A

48VDC Rectifier Plant

19-inch rectifier shelves with optional solar input, LiFePO₄ strings and operation to 75°C ambient.

How the Power Actually Runs

Mechanical services sit upstream of the UPS so cooling never draws on battery autonomy, and a manual bypass lets the UPS be serviced with the load still live.

Swipe the diagram sideways to see all of it

Single line diagram. Grid or generator supply enters the main board, which feeds mechanical services directly and the UPS through its input. The modular UPS with battery string feeds the output bus, with a manual maintenance bypass around it, then A and B rack PDUs supply the dual corded IT load. Grid supply or generator Main board incomer + metering Mechanical services cooling, fans, pumps UPS input rectifier / bypass supply Modular UPS N+1 or 2N, hot swap Battery string lithium or VRLA Manual maintenance bypass Rack PDU A A feed Rack PDU B B feed Dual corded IT load INCOMING UNPROTECTED PROTECTED Single line shown for a typical container. Tier I to Tier IV distribution, dual incomers and 2N UPS are configured to the redundancy target.

Intelligent Monitoring & DCIM

One view across every container on the site

Central
Central operations view monitoring multiple containerised data centre sites
One operations view across every site

Every container on every site rolls up into a single console, so a Pilbara pod and a Sydney edge node are watched the same way, by the same team, against the same thresholds.

Edge
Edge DCIM controller and touchscreen inside a containerised data centre
The controller in the container

An on-board DCIM controller and touchscreen run the container on their own. If the link to head office drops, alarms, interlocks and logging carry on regardless.

Web console SMS alerts Email alerts
Sensors
Leak
Smoke
Door
Temp & humidity
UPS
Precision cooling
Power
Ventilation
Alarm beacon
Intelligent monitoring and DCIM touchscreen for a containerised data centre

Local touchscreen in 10-inch, 21-inch or 42-inch formats, with remote web access.

  • Full visibility of UPS, cooling, power panels and sensors
  • SNMP, Modbus-TCP and BACnet protocol support
  • Remote access by web, with SMS and email alerting
  • Leak, smoke, door, temperature and humidity sensors
  • Integrates with existing BMS platforms
  • Alarms and interlocks keep running if the site link drops

AI Infrastructure: Two Containers, One Cluster

You supply the servers, we supply the facility

GPU platforms in the class of NVIDIA rack-scale systems put 40kW to well past 100kW into a single rack, and they need power quality, thermal capacity and physical security that a plant room retrofit cannot deliver quickly. The answer is to split the problem across two purpose-built containers and deliver both as one commissioned system.

How the Two Containers Split the Job

Battery energy and liquid cooling sit in separate steel boxes, each with its own fire compartment, each scaling on its own clock.

Swipe the diagram sideways to see all of it

Two container AI architecture. Container one holds the main switchboard, modular UPS, battery strings and distribution. It feeds container two, which holds the high density racks, liquid cooling and CDU, rack PDUs and containment, with heat rejected to an external dry cooler or cooling tower. The customer installs only the GPU nodes. SITE SUPPLY Grid or generator CONTAINER 01 Power Main switchboard Incomer, breakers, metering Modular UPS, 250 to 600 kVA Hot swap modules, N+1 or 2N Battery strings Lithium or VRLA, own fire compartment Distribution to compute Busway or cable to Container 02 Power CONTAINER 02 AI infrastructure High density racks You install the GPU nodes. Nothing else. Liquid cooling and CDU Rear door, direct-to-chip or immersion Rack PDUs, containment, cabling Access control, detection and suppression Dry cooler or tower HEAT OUT Both containers are factory built, load tested and commissioned as one system. Add compute containers as the cluster grows.
Heat and hazard stay apart

Battery energy sits in its own fire compartment with its own suppression and detection, so the compute container is free to run a liquid loop at the density AI training demands.

Each half scales on its own clock

Add compute containers as the cluster grows and uprate the power container once, rather than rebuilding a single box every time the GPU count changes.

Deployable where the power is

Compute can go where land, grid capacity and fibre are available rather than where a building already exists. Both containers ship on standard transport.

XRT-AI

Seven Pre-Engineered AI Configurations

Where XRT-CDC is the containerised data centre platform, XRT-AI is the pre-engineered AI infrastructure built on it. Rack nodes at 25, 50 and 90 kW, containerised training halls from 400 to 800 kW using direct-to-chip, rear door or immersion cooling, and multi-pod prefabricated campuses. Every configuration, with its full technical data, is on its own page.

See the XRT-AI range →

Where We Have Already Put Steel on the Ground

Containerised infrastructure earns its keep where a building is slow, expensive or simply not permitted. These are the environments the XRT-CDC platform is already hardened for, and the list is not a limit on what we will quote.

Defence

Deployable and secure

Ballistic rated enclosure options, three-in-one access control by PIN, card or fingerprint, integrated surveillance and a footprint that moves when the mission does.

Read more →
Mining

Dust, heat and distance

IP55 sealed enclosure, operation to +55°C ambient, rock wool insulated envelope and independent internal and external cooling loops that keep dust out of the IT space.

Read more →
Oil & Gas

Corrosive and remote

C5M high corrosion protection for coastal and offshore support environments, salt spray tested construction, and fire rated options up to 120 minutes.

Read more →
AI & HPC

Density without a building

Liquid cooled compute containers paired with dedicated power containers, sited where grid capacity and fibre exist rather than where a data hall happens to be.

Read more →

Container construction

  • Designed to ISO 668 container standards
  • Service life beyond 15 years to ISO 2394:1998
  • IP55 water and dust protection to IEC 60529
  • 750 hour alternating salt spray corrosion resistance
  • Rock wool insulation, heat transfer ≤0.4 W/(m²·K)
  • 1.6mm steel plate walls, 4mm stainless steel floor
  • Operating range -40°C to +55°C, RAL 7035 finish
  • Optional ballistic rating and C5M coastal protection

Racks, fire and security

  • 1800kg static load capacity per rack
  • 600mm or 800mm width, 1100mm or 1200mm depth
  • Sliding rack design for front and rear service access
  • Optional hot and cold aisle containment, CFD modelled
  • Fire rated protection options up to 120 minutes
  • VESDA class early aspirating detection
  • FM200 or Novec 1230 clean agent suppression
  • IP55 three-in-one access control and video surveillance
The full XRT-CDC brochure

Every configuration, the complete construction and cooling specifications, and the deployment detail behind this page.

Download the brochure (PDF)

Your environment is probably on the list even if it is not on this page

Healthcare, utilities, transport, broadcast, research and government have all bought the same platform under a different brief. If you can describe the load, the ambient conditions and the access constraints, we can configure and cost it, including one-off requirements that are not in any brochure.

Put your site in front of us

Why Choose UPS Solutions for Containerised Data Centres

Australian owned critical power and cooling specialists. We design, supply, install, commission and maintain the whole facility, not just the box it arrives in.

Australian field team

Local technicians across Sydney, Melbourne, Brisbane, Perth, Adelaide and beyond, so the people who commission your container are the people who come back to service it.

Tested before it ships

Every unit is built, wired and load tested at the factory with witness testing available, so site works reduce to footings, a supply connection, a data path and final commissioning.

One contract, whole facility

Enclosure, racks, cooling, UPS, batteries, distribution, fire suppression, access control and monitoring under a single scope, rather than five vendors pointing at each other.

24/7 support after handover

Preventive maintenance, battery replacement, cooling service and emergency call-out across Australia, New Zealand and the Pacific Islands, day or night.

Installed and Tested Before Dispatch

A container that arrives half finished is still a construction project. Every XRT-CDC is built, wired, charged and load tested on the factory floor, so what lands on your slab is a facility you can energise rather than a shell to fit out.

  • Enclosure, racks & containment
  • Precision or liquid cooling
  • UPS, batteries & distribution
  • Fire detection & suppression
  • Access control & surveillance
  • DCIM monitoring & alerting
XRT-CDC containerised data centre with side access panels open, racks installed and tested before dispatch

Containerised Data Centre FAQs

The questions we are asked most often when scoping a containerised data centre, switchroom or power train unit.

What is a containerised data centre?

A containerised data centre is a complete data centre built inside a shipping container sized enclosure. IT racks, precision cooling, UPS, batteries, power distribution, fire suppression, security and monitoring are all installed and tested at the factory, so the unit arrives on site as a finished facility rather than a shell to fit out. It is also called a modular, prefabricated or container data centre.

What is a containerised switchroom?

A containerised switchroom is an ISO container fitted out as a complete electrical room, with switchgear, distribution, protection, metering and environmental control installed and tested in the factory before it ships. It is the same build approach as a containerised data centre, with the electrical infrastructure as the payload instead of IT racks. Outside Australia the same product is usually called an e-house. XRT-CDC covers both, and the two are frequently ordered together so the switchroom and the IT container arrive as a matched pair.

What is a power train unit (PTU)?

A power train unit is a prefabricated module that carries the whole electrical path feeding an IT load: transformer, switchboard, UPS, batteries and output distribution, integrated and factory tested as one assembly. It is also called a modular power skid or a prefabricated power module. Building the power train off site means the electrical works stop being the critical path on your programme, because the module arrives commissioned rather than being assembled in a live building. XRT-CDC power train units are available in N, N+1 and N+N configurations.

Is a containerised data centre the same as a modular or prefabricated data centre?

They overlap. Modular data centre is the broadest term and covers any facility built from repeatable prefabricated blocks, whether those blocks are ISO containers, skids or purpose built modules. A containerised data centre is the subset built inside shipping containers, which is what makes it transportable on standard road and rail. A prefabricated data centre means the same thing as modular in most Australian tenders. XRT-CDC is all three.

What is an edge or micro data centre?

An edge data centre puts compute close to where the data is created rather than in a capital city colocation facility, which cuts latency and the cost of backhaul. In Australia that usually means a mine site, a port, a telecom exchange, a regional hospital or a 5G aggregation point. A micro data centre is the smallest form of this, typically a single rack or a 10ft container. XRT-CDC starts at that scale and uses the same components as the multi-container builds, so the spare parts and the support contract are common across your fleet.

How many server racks fit in a 20ft or 40ft container?

The XRT-CDC layout holds up to 8 racks in a 20ft container and up to 18 racks in a 40ft container, because the cooling is wall mounted rather than occupying a separate condenser section. A conventional split cooling container of the same size typically takes four racks. A dual bay configuration of two 40ft containers takes up to 32 racks with a central contained aisle.

Can a containerised data centre run AI and GPU workloads?

Yes. High density AI and HPC racks are handled with liquid cooling rather than air, using rear door heat exchangers, direct-to-chip cold plates or immersion tanks. The common pattern for AI is two containers: one holding the UPS, batteries and distribution, and a second holding the liquid cooled compute racks. The customer installs their GPU nodes and the facility is otherwise complete.

Can I add a container to house my existing UPS?

Yes. A container switchroom for an existing UPS is one of the more common XRT-CDC applications, particularly where a site has outgrown its electrical room but the UPS itself still has service life. We build the enclosure, cooling, distribution and environmental monitoring around the equipment you already own, rather than requiring you to replace it. The XRT-CDC range is UPS agnostic, so client supplied gear is supported.

What cooling options are available?

Wall and side mounted cooling from 5.5 to 31.5kW, in-row cooling from 5.6 to 90kW, room based cooling from 5.5 to 122.9kW, top mounted cooling, and liquid cooling for high density AI workloads. Direct and indirect free cooling are available to reduce PUE, with indirect free cooling reaching a PUE as low as 1.2 and direct free cooling with hybrid air technology as low as 1.1 in favourable conditions.

What UPS capacity can be installed in a container?

From 3kVA rack mounted units up to 600kVA modular floor standing systems in a single container, plus 48VDC rectifier plant from 60A to 1200A. Multi-megawatt capacity is achieved by deploying dedicated power containers alongside compute containers in a multi-container configuration.

How long does a containerised data centre take to deploy?

Because the unit is prefabricated and factory acceptance tested, deployment is typically around 20% faster than an equivalent traditional build, and site works reduce to foundations or footings, a power connection, a data path and final commissioning. Lead time depends on configuration, cooling selection and UPS sizing, so we quote it against your specific brief.

How much does a containerised data centre cost?

There is no single list price, because the cost is driven by the IT load in kW, the redundancy target, the cooling architecture and the site conditions rather than by the size of the box. A 10ft edge enclosure with a single rack and a small UPS sits at one end of the range and a liquid cooled 800kW AI hall with 2N power sits at the other. Send us the rack count, kW per rack, redundancy target and site location and we will put a configured price in front of you rather than a range.

Will it survive an Australian mine site or coastal installation?

The enclosure is IP55 rated, salt spray tested, rock wool insulated and rated for operation from -40°C to +55°C, with optional C5M high corrosion protection for coastal and offshore environments and fire rated construction up to 120 minutes. Cooling uses independent internal and external loops so dust and moisture do not enter the IT space.

What is the difference between XRT-CDC and XRT-AI?

XRT-CDC is the containerised data centre platform: the enclosure, racks, cooling, UPS, distribution and monitoring, configured to whatever the site needs across defence, mining, oil and gas or general IT. XRT-AI is a set of seven pre-engineered configurations built on that same platform specifically for accelerated computing, from a 25kW single rack node up to an 800kW liquid cooled containerised hall, plus multi-pod AI farm campuses.

Do you install and maintain the container after delivery?

Yes. UPS Solutions designs, supplies, installs, commissions and maintains the complete system across Australia, New Zealand and the Pacific Islands, including preventive maintenance, battery replacement, cooling service and 24/7 support.